Posting operational work (Subcontractors) – part 7

In my previous six posts I described posting of own work on projects, using different models. The base characteristics of this models is that we have our own resources and items consumption. Now, we have once more model for posting, when we use Subcontractors work. Target is the same, we need to make some contracted Construction Positions, but now we do not use own consumption.

We have two types of subcontractor’s engagement in our construction projects:

  • First, we can engage subcontractor for do some minor work on our positions. That means, we will work some part of job, and some part of job will made by subcontractors.
  • Second, we can engage subcontractors for doing complete job by position. This is very often when we work on complex construction with very vary business processes, as construction of houses, buildings, etc., because the main constructor often perform only one or two types of works and engage subcontractors for all other works.

I describe how we can planning that in Construction Position Norms in my old post about Construction Position and Norms – Cost Analyze and Bill of Quantities – (Subcontractors), but now I will describe posting of subcontractor usage.

Subcontractor’s minor engagement

This is the simply process. We get invoice from subcontractors for their part of work. For posting, we will use the standard NAV purchase documents, Purchase Order or Purchase Invoice. We will post this as our cost using G/L Account, but we must to set Job No. and Job Task No. in Purchase Lines. When we post document, we will get Job Ledger Entries with G/L Account types. Our own part of job, we will post using Job and Position Journals or using Output Orders. We will invoice position we posting using Position Journals or Output Orders, with the same quantity.

We can use this model for all planned or unplanned costs on project. NAV will be classifies our own usage as resource cost or as item cost, and all other costs as G/L Costs.

As I said, this is very simply process. Other posting method need more customization or more manual work. We choose customizations, and we make automatic model of subcontractors posting in our solution NAV4Construction.

Subcontractor’s complete position engagement

In this example, we engage subcontractors for doing complete job by position. We get invoices/certificates from them for complete position engagement as we have this job in our Bill Of Quantities.

Doesn’t meter I said is too complex process, we mad it simply. For posting, we will also use the standard NAV purchase documents, Purchase Order or Purchase Invoice, but with some customizations. We will post this using Position types (new NAV4Construction type), and we also must to set Job No. and Job Task No. in Purchase Lines.

Image

When we post this document, we will get Job Ledger Entries with G/L Account types (G/L Account from Posting Groups) as cost, and also Position Ledger Entry with output quantity and price from BoQ, and posting type Subcontractor, as well. With only one posting, we will get complete posting process, and we can prepare our invoice to customer.

Construction Project Management Software

This article is borrowed from Dexter+Chaney blog, because I think it is a great story and it is related with my topics:

– – –

When it comes to project management software, contractors have numerous options, from spreadsheets and generic applications to software designed for the construction industry. I recently read an industry survey on the subject that not only provided some interesting insight, but also confirmed the things I’ve been saying about project management software.

The Benefits

It came as no surprise that ranked in the top five project management software benefits were access to detailed project documents, better collaboration, and faster document approvals. In my opinion, the next generation of project management software will not only provide document storage in a centralized location, it will foster better communication between project team members, resulting in more efficient and profitable projects. In fact, survey participants indicated that specialized software for construction had the best record of helping contractors come in under budget on their projects.

The Results

I know I’ve talked a lot about the potential benefits of construction specific project management software, but you may be wondering, “What about the real results?”Well, according to the survey, participants indicated that by using project management software they saw improved accountability from document control, better financial visibility, and improved collaboration. Considering the fact that these three issues are the ones that come up most often when I speak to project managers about their challenges, I feel pretty good about the role software plays in addressing them.

4 Mistakes to Avoid in Construction Bidding

This article is borrowed from Dexter+Chaney blog, because I think it is a great story and it is related with my topics:

– – –

I’m pleased to introduce Byron Largen, CPA from Mountjoy Chilton Medley LLP (MCM), as this week’s guest blogger. MCM is a CPA firm with a team of accountants dedicated to construction accounting.

Construction markets remain competitive, so it comes as no surprise that construction companies have to be at the top of their game throughout a project. One of the biggest stumbling blocks, though, is often at the beginning of a project – during bidding – but there are key areas to avoid in order to make sure your teams stay on track.

1. Overlooking Your Indirect Costs

With advanced construction software to help you, identifying your direct costs on a job is probably pretty easy. But one area that leads to problems is forgetting the indirect costs — those not directly attributable to the project at hand but still likely to be in play.

For example, if you completely own a piece of equipment, you probably estimate the amount of fuel that it uses on a job, but may not consider including the depreciation, insurance, maintenance, and other costs associated with running it. All of these expenses are important to include for your bid to be accurate.

2. Missing the Mark on Profitability

With an ongoing shortage of construction jobs, it can be tempting to bid at every one that comes along, whether or not they’ll actually earn you a profit. That said, calculating profit margin can be tricky, so be sure you don’t undercut your own profitability as the number start flying. Use historic job performance as a predictor, be sure you have the latest labor rates and material prices, and if the math doesn’t add up to profitable work, be prepared to walk away.

3. Not Keeping Up with Technology and Construction Software

Used correctly, technology can give you a competitive edge For example, bids generally begin with estimates. And how can you improve your estimates? By upgrading your technology.

With the multi-dimensional capabilities of BIM now integrated into many software applications, estimators can see all angles of their work in vastly more detail than before. For instance, an estimator can separate construction components from the overall structure to scrutinize them individually.

4. Ignoring the “Other Guys”

Don’t make the mistake of underestimating your competition. When working on a bid, you’re assessing the project with respect to your company’s capabilities, but if you consider the competition, it may change the way you bid, or even your decision to bid. If two of your main competitors are known for bidding low, you may have to reduce your bid comparatively. Is the job still worth it?

Science Meets Art

Some contractors might say that bidding is a science — you crunch the numbers and stick to them. Others might say that it’s an art — when your gut says a project will be profitable and elevate your visibility in the marketplace, go for it.

The truth probably lies somewhere in between. Now more than ever, you’ve got to do the math and make sure your cash flow can handle the burden of every job. But, at the same time, no one knows your local market and construction company like you do. So your gut certainly deserves a say.

Posting operational work (Construction Management) – part 1

In NAV4Construction, we can post the operational work on next ways:

  • Using ‘Output Order’ – posting of Construction Position output work and Resource and Item consumption per Project in the same time;
  • Using ‘Position Journal’ – posting only Construction Position output work per Project; we need to post consumption separately;
  • Using ‘Job Journal’ (standard NAV functionality with some specific customizations) – posting only Resource and Item consumption per Project; we need to post output separately;

Advantage of the first method is that we can post all entries with the one document. We get posted document with ‘Navigate’ functionality. Also, this method enables us to have complete statistic of cost per every Construction Position for each Project. Failing of this method is that if we have many complex position works per day, it is too complicated to make evidence and post it.

If we choose posting without ‘Output Order’, we get simply procedure for posting. We use ‘Position Journal’ for evidence of work per all Construction Position we have and separately we use ‘Job Journal’ for evidence of consumption all Items and Resources, not linked with Construction Positions. On this way we get simpler method, but we lose connection of consumption with Construction Position output. We cannot get all things and we must to decide what method we want. Good thing is that we can choose different method for each project, depend of complexity and project requirement.

Output Order

New ‘Output Order’ we get with ‘New’ command on the ribbon. We need to put Project and Task we work on them and choose Construction Position for posting. System will make automatic filter for positions and we get only positions we define on Bill of Quantities.

Image

If we eventually must post position out-of-BoQ, we can press ‘Show All’ and we will get complete Construction Position code list. After that, we need to fill ‘Quantity’ field with output quantity for this position in presented Unit of Measure. If this is not first posting for this position on this project, we can see previous posted quantity for this position. We also can see contracted position quantity from BoQ. On this way, we have control before posting this values. If we want to see what we post for this position previous, we can press on ‘Position Executed Quantity’ field and we will get complete evidence from Position Ledger Entry.

Image

We can fill another specific filed, depend of construction type (civil-engineering, building construction, road, maintenance…), but I will explain this in some other posts.

When we fill all necessary header fields, we have to fill lines with consumption data. We can fill lines automatic or manually. Results is the same, but automatic can make work easier if we have good normatives for construction positions.

Automatic fill process can be started by the ‘Import outputs’ command. System will use all normative lines for position in header, recalculate consumption quantity with position quantity on header and fills it. I have to notice, these are planned quantities and I am sure, we need to change some of them.

If we have manually input of data, we need to choose line Type (Resource or Item) and choose desired Resource/Item. After that, process is different depend of line type:

Item

For Item, we need to fill ‘Location Code’. We can get default location code for project if we make this setup on Project Card. We need to fill item quantity, as well and this is all. All costs and prices for the item will be filled automatically.

Resource

For Resource, we can fill more fields. There are not all mandatory and this depend of setup for company and/or project. It is necessary to fill quantity per Unit of Measure and we can choose ‘Work Type Code’ for different Unit of Measures/Cost/Price. If this is people type of resource, this is enough and as items, costs and prices will be automatic filled. But if we choose machine resource type, we can fill more fields.

First of them are ‘Waiting Time’ and ‘Extremely Stagnation Time’. ‘Waiting Time’ is time when resource did not work because bad organization. System will be calculate cost for all quantity time, but price for (‘Quantity’ – ‘Waiting Time’) if ‘Waiting Time’ is acceptable. If this time is not acceptable, system will calculate price based on specific formula (this is very complex setup, and I will explain it in independent post). ‘Extremely Stagnation Time’ is time we use only for evidence. This is a time when we was prevented for work (nasty weather or some other force majeure).

We can fill ‘Mechanization Resource Code’ if we know exactly what machine is worked. System can propose only machines for choosing resource. If we in advance know what machine worked, we can fill this field, and ‘Resource No.’ will be filled automatically. If we have configured machinist for mechanization resource, this field will be filled automatically, but if we have not it, we can choose ‘Employee No.’ for machinist from filtered employee list only from departments who use machines.

Know we know what time machines spend for making position, but we don’t know what they are worked exactly. Because of that, we have ‘Ongoings Code’ where we can define what our machine really do. ‘Ongoings Code’ list has Unit of Measures and they are configured depending resource types. When we choose this code, we need to fill ‘Ongoings Quantity’.

If our machine is the vehicle, we can fill additional fields: ‘Mileage’ and ‘Tour Quantity’.

This is only base story about this process and I will detailed explain some specifics in some new posts.

Posting

Before posting, we need to change status. Changing status make checking of all necessary fields input. NAV will make evidence of username, date and time for making document and for status changing, because these are very important data.

After that, posting process is simply. For each posted document, we can make storno (correction) document very easy, but I will explain it in later posts.

Bill of Quantities – (Q&A) part 7

I get few questions about work in Bill of Quantities from my friends, and I will try to give answers.

Questions:

1)    When we have too much construction positions (I speak about thousands), how we can import the fast. This is usually case in building construction.

2)    When our customers/investors require from us quote in special file, how we can prepare that. We would not refuse big job because of that.

Answers:

1)    We have two solutions. If we already have this positions in our construction positions code-list, we can use command ‘Import from Excel’; we need prepare file with codes and quantities and NAV will import them. If we have not these positions (usually we have not them), we have specific function we call ‘Massive positions import’. This function import all positions from Excel; if we have this position in our code-list it is fine, but if we have not, NAV will create them in Construction Position code-list and add them Unit of Measure. Depends of description length, system will fill only description fields or will create extended text. Also, system will create Cross-reference code for this specific project and if we want create Normative Headers. Except creating in Cons.Position code-list, NAV will fill all BoQ lines.

2)    All users or partners can modify or make new Quote report. But, if this is not enough, because come customers can require that you must fill their Excel files, we have command ‘Export to Excel’. This is not perfect solution and system is not magical L, but it can help to reduce time to prepare document. We can export all important data to Excel file. You need to repack in required document design.

I am not explain all BoQ functionalities in my posts, but this is enough to understand way of working. If you have some other questions, I expect them and I will try to give you an answer.

Bill of Quantities – (Subcontractors) part 6

As I wrote in my old posts, we can add subcontractor works in planned construction position normatives. We can plan in one normative, part of job works by ourself and part of job works by some subcontractor. When we prepare normative, we usually don’t know which subcontractor will work for us. Because of that, we make plan that job will work some subcontractor.

When we make Bill of Quantities, for all construction position lines where planed subcontractor in their normative is, NAV will be marked field ‘Subcontractor’. For this lines, we can fill ‘Quote Inquiry’ for potential subcontractors.

Image

For all this lines, we can start command to print documents for their tender competition. This command is ‘Query for Quote’ and it can print document or prepare Excel file to send to potential subcontractors. We can choose to print expected price or not (only lines).

Image

NAV will create as many request files (or documents) as we set different Quote Inquiries in Bill of Quantities lines.

When we get all quotes, we need to insert in NAV. If we get Excel quotes, we can use automatic function for import. After that, we can use functionalities for choosing the best quote, individual for each position, or as complete quote. More about choosing the best quote of Subcontractors, I will explain in some other posts.